# Cost and time

> Give process steps a cost and a time, and see the diagram's total cost, total time and end-to-end time.

## What it's for

You can record what each step of a process costs and how long it takes, then see the totals for the whole diagram. Use it to size the current process, compare it with a future state, or show where the time and money go.

Nothing about cost and time appears on a board until someone adds a value, so boards that don't use it look exactly as before.

## Adding a cost or time to a step

1. Select the step (or any other process element, such as an event, decision or data object).
2. In the inspector (top right of the canvas), fill in:
   - **Cost (A$)**: the cost of doing the step once, in Australian dollars, for example `120` or `85.50`.
   - **Time**: how long the step takes, with the unit next to it: **min**, **h** or **days**. A day is 24 hours.
3. Click away or press Tab. The value is saved for everyone straight away.

To remove a value, clear the box. Notes (annotations), [states and risks](states-and-risks) don't have a cost or time.

A step with a cost or time shows a small badge at its bottom right, for example "$120 · 2 h".

You can also tell the live AI, for example "approving the claim takes the manager about twenty minutes" or "each payment run costs us fifteen dollars". It records the cost and time on the step.

## The totals

Once any element has a cost or time, a **Totals** panel appears at the bottom of the canvas:

- **Total cost**: every element's cost added together.
- **Total time**: every element's time added together. This is the effort if every step happens once.
- **End to end**: the longest chain of times along the flows, from the start of the process to its end. Alternative paths after a decision and steps that run in parallel are only counted once (the longest one wins), and rework loops (going back to an earlier step) are left out. It only shows when it differs from the total time.

Totals add up each step once. They don't know how often a decision goes each way or how many times a loop repeats.

## Comparing states

If the board has [states](states-and-risks) such as Current and Future, filter the diagram to a state with the bar at the top of the canvas. The totals panel then shows **Totals for "Future"** (or whichever state you picked), counting only the elements in that state. Switch between states to compare their cost and time.

## In exports

- The business requirements document shows each step's cost and time next to it in the process description, and a **Totals** line for the diagram.
- Cost and time aren't part of the BPMN 2.0 standard, so the BPMN export doesn't include them.

See also [Editing the diagram](editing-the-diagram) and [Exporting](exporting).